Principal Investigator:Wright, Greg T Licensed Year(s):
2018
Summary:
The objective of this project is to identify for closures sites with no unacceptable risks and to develop an action plan for additional work for any sites that cannot be closed.
Twenty-two sites will be visited to collect soil, surface water (where available) and vegetation samples to determine levels of previously identified contaminants of concern. The work plan for each site involves soil, s...
Principal Investigator:Hamilton, Melissa M Licensed Year(s):
2013
Summary:
The purpose of each Phase I/II Environmental Site Assessment (ESA) is to determine the current environmental and physical conditions at each site to allow for the potential future development of the appropriate remediation or risk management strategies and costs. This will include the identification and quantification of environmental impacts to all media including soil, sediment, surface water a...
Principal Investigator:Bartlett, Mike Licensed Year(s):
2012
Summary:
The objective of the research project is to monitor the surface water quality in Bosworth Creek. Data from sampling stations established within and downstream of the Site will be compared to upstream reference stations, located beyond the possible influence of the development, and against an appropriate range of regional data indicating natural variability (where available). Stations will be monit...
Principal Investigator:Lennie-Misgeld, Peter Licensed Year(s):20112010
2009
Summary:
This licence is being issued for the scientific research application no. 982.
The objective of this research is to characterize the surface water hydrology at the Thor Lake site and vicinity for at least one hydrologic year. The baseline study is being conducted to aid Avalon Ventures in assessing potential environmental effects of its activities and having adequate environmental information to...
Principal Investigator:Kustan, Ed Licensed Year(s):
2005
Summary:
The research team, including an environmental consultant, a technician, and a member of the community, will access the site and assess the site conditions. The field will be accessed from Fort Liard via the barge. The individual sites will be accessed via truck. At the site, researchers will complete a walk around of the site including the site facilities and surrounding area. Should any soil or s...
Principal Investigator:Kustan, Ed Licensed Year(s):
2005
Summary:
The research team, including an environmental consultant, a technician, and a member of the community, will access the site and assess the site conditions. The field will be accessed from Fort Liard via the barge. The individual sites will be accessed via truck. At the site, researchers will complete a walk around of the site including the site facilities and surrounding area. Should any soil or s...
Principal Investigator:Kustan, Ed Licensed Year(s):
2005
Summary:
The research team, including an environmental consultant, a technician, and a member of the local community, will access the site and assess the site conditions. The researchers will access the site via helicopter and will complete a walk around of the site including the site facilities and surrounding area. Should any soil or surface water be identified as a concern, a sample will be obtained and...
Principal Investigator:Kustan, Ed Licensed Year(s):
2005
Summary:
The research team, including an environmental consultant, a technician, and a member of the local community, will access the site and assess the site conditions. The researchers will access the site via helicopter and will complete a walk around of the site including the site facilities and surrounding area. Should any soil or surface water be identified as a concern, a sample will be obtained and...
Principal Investigator:Weagle, Ken V Licensed Year(s):2005
2004
Summary:
The purpose of this fieldwork is for the collection of baseline data to support an anticipated application to the Mackenzie Valley Land and Water Board. There are 5 main components of the program. 1) Air quality and climate; General air quality will be m...
Principal Investigator:Miller, Samantha Licensed Year(s):200620052004
2003
2002 Summary:
The Pointed Mountain Gas Plant, four associated wellsites, and some associated infrastructure are being decommissioned. The site was originally constructed in 1966 and has been shut down since September 2001. Previous environmental work and public consul...